GanttWorkingHour (Function) In french: GanttHeureOuvrable Overwrites the working hours on a row in a Gantt Chart column in a Table or TreeView Table control.
GanttWorkingHour(COL_Gantt, 2, "0930", "1200", "1300", "1830")
GanttWorkingHour(COL_Gantt, 3, "1000", "1700")
Syntax
GanttWorkingHour(<Gantt column> , <Row> , <Start time> , <End time> [, <Start time 2> [, <End time 2>]])
<Gantt column>: Control name Name of the Gantt Chart column (in a Table or TreeView Table control) to be used. <Row>: Integer Number of the row to modify. Note: The line associated with a task can be identified by the Property Line property of the GanttTask type variable. <Start time>: Character string or Time variable Start time of the first working time period. <End time>: Character string or Time variable End time of the first working time period. <Start time 2>: Character string or Time variable Start time of the second working time period. <End time 2>: Character string or Time variable End time of the second working time period. Remarks - For the non-specified rows, the hours used are:
- This function affects the drawing of the Gantt chart if the hours are displayed in the Gantt chart.
- This function affects the calculation of the task duration if the tasks are specified in hours.
- Two time periods can be used to define the working hours for the morning and for the afternoon for example.